Picture of the current outdated Fire Station #1 that is set to be replaced with a modernized facility.

Safety

Fire Station 1 Replacement

Updating City Facilities

We are pleased to announce a significant development that will positively impact our city's firefighting capabilities and infrastructure. In line with our commitment to progress and efficiency, we have initiated plans to replace two aging facilities: Fire Station 1 located on Dawson St, and the Fire Administration Building situated on Martin St.

The new facility will consist of a multi-story complex spanning 50,000 square feet. This initiative reflects our dedication to ensuring the highest standards of emergency response and service delivery for the benefit of our community.

Key aspects of this project include:

  • Five planned bays equipped with state-of-the-art technology and resources.
  • A prime location facing Salisbury St, strategically chosen to optimize accessibility and operational effectiveness.
  • Serving as a vital anchor for the vehicular gateway from MLK Jr Blvd into downtown Raleigh, underscoring our commitment to safeguarding the core of our city.

Project Details

 
Type:
City Properties and Facilities
Budget:
$72 m
Contractors:
Designers- Schrader Group - A Hord Coplan Macht Studio - Construction Managers at Risk (CMAR) - Brasfield & Gorrie

Contact

 

 

Project Manager
Stephanie Seeber, PA AIA
[email protected] 
919-996-5579 

Lead Department:
Engineering Services
Participating Department:
Fire

Subscribe

 

Planning

The Fire Station 1 and Fire Administration project is currently working through the programming and conceptual phase. This phase evaluates the program and operational needs for the project stakeholders. The site will be analyzed based on the project requirements, parcel size, and zoning restrictions. The future site of Fire Station 1 is located on the corner of S Salisbury and Martin Luther King Boulevard. Conceptual designs will be generated for consideration at the end of this phase.

Lead Department:
Engineering Services

Project Schedule

DateActivity 
Current Programming/Conceptual Phase
Summer 2025Design Starts
Fall 2026Construction Bidding 
Late Fall 2026Start Construction 
Early 2029Project Complete 